Projects > Pennsylvania > East Stroudsburg - Snow Melting Asphalt Retrofit

Residence in East Stroudsburg, Pennsylvania

Single snow melting system installed that covers approx. 300 sq. ft.

Snow melting system retrofit into asphalt driveway



Asphalt driveway to be retrofitted with snow melting system

The asphalt driveway before installation of the snow melting cable.

Click on images to enlarge

Control unit for heated driveway snow melting system

240 V. 30 amp breaker is supplied by a certified electrician - the control unit is hung in the garage between two studs.

Cutting grooves to retrofit asphalt driveway with radiant snow melting system.

Six hundred lineal feet of lines are marked on the driveway. Lines are spaced at 6 inches

Retrofitting driveway with electric snow melting system

A professional saw cutter cuts grooves in the asphalt 1 to 1½-inches deep and ¼-inch wide.

Heat cable is installed in grooves cut out from driveway.

Six hundred lineal feet of heat cable is laid in the newly cut grooves.

Backer rod placed over heat cable in grooves.

Backer rod (a foam filler) is used to fill in space between the heat cable and sealant.

Installing driveway snow melting system.

The cable was laid out to heat a pair of 2 ft wide tire tracks up the middle and an area to exit and enter at the bottom and top of the driveway. Backer rod nearly complete.

Connecting wiring of snowmelt system.

The heat cable is spliced to cold lead, which connects to the transformer inside the control unit.

Sealing grooves where heat cable was installed.

The grooves are then sealed with a blacktop sealant to prevent rocks and other sharp objects from damaging the cable

Finished driveway retrofitted with radiant heat snowmelt system.

Close up picture of sealed driveway - The sealant used is black and blends in well with the asphalt

Snow sensor for heated driveway mounted on roof.

This system is activated by an aerial mounted snow switch and a manual overriding 12-hour timer in the garage.

Completed installation of driveway snow melting system.

Final picture of an installed snow melting system. The system is not very noticeable now, but it will be come the first snowfall.